CONCRETE PAD: 6 ft. x 6 ft. (1.8m x 1.8m) depth to be below frost line in your area. Pad should remain approximately 6" above finished grade level. FINISHED SURFACE SHOULD BE LEVEL. Recommended concrete to be used is 15- 20 MPa or 3000 psi with 20mm regular stone, no reinforcement in the pad is necessary but may be added for extra strength.
NOTE: See electrical requirements before completing concrete pad.
|
|

|
|
| Electrical Requirements: |
|
A trench is required excavate a trench from the foundation site to the location of the control panel and another from your control panel to your power source.
|
| Control Panel: |
|
The control panel should be situated adjacent to the main gate opposite the gate opening this will ensure that horses can be easily lead into the exerciser while the control panel is manned by the trainer. The depth of this trench should meet local electrical code for buried wire. The weatherproof control panel does not require separate housing.
|
| Conduit: |
|
Install two 1" PVC conduits from the control panel location to within 12" from the center of the foundation and another 1" PVC conduit from the power source to the control panel (see illustration). Placing a wire or thin rope in the conduits aids in pulling of the power cables from the control panel to the motor.
|
 |
| ELECTRICAL NOTE: |
|
You will also need enough 30amp 220v 2-wire plus ground single phase cable to power the control panel (i.e. from your power location to the control panel), 20amp 3-wire plus ground cable to connect the exerciser's motor to the control panel and 14 gauge 2-wire to connect the fencer to the control panel (consult an electrician if you are considering other cable options). Some installations and electrical requirements may vary depending on local codes. If using a center pole application then under gate cable will be used instead of the 14 gauge 2-wire.
|